Why should the bleeder valve be opened before opening the hydrant gate during a transition to hydrant supply?

Prepare for the NFPA 1002 Pump Operations Test with our comprehensive quiz. Utilize flashcards and multiple choice questions, complete with hints and detailed explanations, to ensure you're ready for exam day!

Multiple Choice

Why should the bleeder valve be opened before opening the hydrant gate during a transition to hydrant supply?

Explanation:
Vent air from the line so water can fill and flow smoothly when the hydrant gate is opened. Opening the bleeder first releases trapped air in the supply line, preventing air locks and reducing the risk of water hammer or losing pump prime when the hydrant gate is opened. Once the line is vented and water begins to flow, you can then open the hydrant gate.

Vent air from the line so water can fill and flow smoothly when the hydrant gate is opened. Opening the bleeder first releases trapped air in the supply line, preventing air locks and reducing the risk of water hammer or losing pump prime when the hydrant gate is opened. Once the line is vented and water begins to flow, you can then open the hydrant gate.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy